Centre seeks to expedite interlinking of rivers

3 Comments
Author(s): Bharat Lal Seth
Date:Jul 4, 2013

Water resources ministry publishes draft guidelines for water sharing amongst states seeking greater role for the Centre in water resource development

The 802 km Cauvery river has 32,000 sq km basin area in Karnataka and 44,000 sq km basin area in Tamil Nadu

It is hardly a state secret that the water engineering community in India wants to expedite the Interlinking of Rivers (ILR) project. To move on the issue, the Union Ministry of Water Resources last month uploaded on its website draft policy guidelines for sharing of water amongst states, with the altruistic objective of “developing the waters of inter-state rivers for the betterment of the population of the co-basin states/union territories such that developments are not detrimental to the interests of one another and are guided by national perspective”. A few pages into the document make it clear that the draft is geared to create policy influence; states are encouraged to import from one area to another, and also export to deficit basins outside state territories.

The draft document recommends a basin authority or board be constituted including co-basin states under the aegis of the Centre with ‘executive powers’ capable of monitoring and implementing the allocations of a shared river. “What is wrong with wanting to expedite the ILR project? We in the water engineers’ community believe in it, and after the judgment by the Supreme Court on February 27, 2012, the State is duty bound to work towards it,” says Chetan Pandit, former member (policy and planning), Central Water Commission, the technical wing of the water resources ministry.

Helsinki Rules
 

The relevant factors which are to be considered include, but are not limited to:

  • The geography of the basin, including in particular the extent of the drainage area in the territory of each basin state;
  • The hydrology of the basin, including in particular the contribution of water by each basin state;
  • Climate affecting the basin;
  • Past utilisation of the waters of the basin, including in particular existing utilisation
  • Economic and social needs of each basin state
  • The population dependent on the waters of the basin in each basin state
  • The comparative costs of alternative means of satisfying the economic and social needs of each basin state
  • Availability of other resources
  • Avoidance of unnecessary waste in the utilization of waters of the basin
  • Practicability of compensation to one or more of the co-basin States as a means of adjusting conflicts among uses The degree to which the needs of a basin state may be satisfied, without causing substantial injury to a co-basin state
 

The apex court in February last year expressed “pious hope of speedy implementation” of the ILR project and mandated the formation of a committee to “ensure the completion of projects so that the benefits accrue within reasonable time and cost”. The judgment includes a mandamus to the committee to meet at least once in two months; it also must submit a bi-annual progress report to the cabinet at the Centre. The committee formed recently is yet to convene on the issue.

First cut seems vague

Talk of a policy on water sharing began in 1998 as the second national water policy, instated in 2002, was being drafted and the Cauvery water sharing issue was making headlines. The Central Water Commission was tasked to prepare a draft, which was later circulated to the States. The entire draft was hinged on the fact that water resource development should be planned for a hydrological unit such as a drainage basin or for a sub-basin, taking in to account water for sustainable use. No controversy here; in the federal structure the state has exclusive power over water, although the Parliament has the overriding power of legislation for regulation of inter-state rivers and river valleys in public interest.

The National Water Resources Council, chaired by the Prime Minister, constituted a working group under the secretary, Union Ministry of Water Resources in 2002 to advance the matter. But even after a few years of deliberations there was no consensus. “Since it was a politically sensitive issue, the concept was deferred”, said an official. The objective of the policy is to provide clarity to the issue of water sharing. “The international guidelines such as the Helsinki rules, 1966, (see box) are vague and confusing”. The idea, say officials, was to help serve negotiation before setting up a tribunal. But the draft itself is a ‘first cut’, and vague. An official even went as far as calling the draft and drafting process “eyewash”.

The draft covers the water of shared river basins, not including the direct use of rain water by the user in the state. The storage of water or diversion of water from a natural stream is accounted for. Clearly this is worded to allow for rainwater harvesting through recharge techniques, although it neither defines this nor alludes to other interventions such as storm water management for a city. According to the ministry of water resources, artificial recharge has a potential 4 per cent share of the water available in the country. “Not including rainwater harvesting in the water allocation equations serves as a disincentive, as now states can exploit this without it counting as consumptive use,” said a senior official of the ministry.
    
Divert water from agriculture to industry

A controversial aspect is the fact that allocation priorities are being done away with  again. The draft states that “priority of uses could differ from state to state and even within regions in the same state”. The draft goes on to state that whilst priority of use and consequential priority needs can be considered during the process of determining the sharing or distribution, in reality it need not be qualified for a particular use. “The state should normally be free to use its share of water for any beneficial purpose unless specific restrictions are warranted from over-riding national priorities, without detriment to the interests of other co-basin states”. If the goal is more dollars per drop then there is fear that water will be re-allocated from agriculture to industry and commercial purposes. 
 
State governments often give in to increasing monetary output per drop use, which promotes allocation of water from agriculture to industry, and may at scale threaten food security. Diversion to urban and industrial conurbations is a reality and often leads to conflicts, Maharashtra being a case in point. “Since 2003, 1,500 million cubic metre of water has been diverted from agricultural allocations to urban or industrial use in Maharashtra. This has implications for 357,600 hectare in the state or 300,000 families, assuming an average 1 hectare land holding.

This diversion is now a fait accompli,” said K J Joy, convenor of the Forum for Policy Dialogue on Water Conflicts in India, an initiative to bring together researchers on the issue. Even if Joy’s figures are disputed by the state government, and agricultural water use efficiency is sought, it is clear that the policy may set a dangerous precedent and threaten the agrarian economy.

The ministry has invited comments on the draft policy until July 31, and can expect a barrage of comments from stakeholders who believe that while such allocation transfers are harmful, the projected costs of inter basin water transfer projects too most often outweigh the stated benefits.

 

AddThis

Good article.
The Indian Rivers Inter-link is a proposed large-scale civil engineering project that aims to join the majority of India's rivers by canals and so reduce persistent water shortages in parts of India.
In 1972 the then Minister for Irrigation K. L. Rao proposed a 2640 kilometer long link between the Ganges and Kaveri rivers. In 1974 plans were proposed for the 'Garland canal'. In 1982 the National Water Development Agency was set up to carry out surveys of the links and prepare feasibility studies. The Garland Canal was proposed by Dinshaw J. Dastur, a consultant Engineer
The Inter-link would consist of two parts, a northern Himalayan River Development component and a southern Peninsular River Development component.
The northern component would consist of a series of dams built along the Ganga and Brahmaputra rivers in India, Nepal and Bhutan for the purposes of storage. Canals would be built to transfer surplus water from the eastern tributaries of the Ganga to the west. The Brahmaputra and its tributaries would be linked with the Ganga and the Ganga with the Mahanadi river. This part of the project would provide additional irrigation for about 220,000 square kilometres and generate about 30 gigawatts of electricity. In theory it would provide extra flood control in the Ganga and Brahmaputra river basins. It could also provide excess water for the controversial Farakka Barragewhich could be used to flush out the silt at the port of Kolkata.
The main part of the project would send water from the eastern part of India to the south and west. The southern development project would consist of four main parts. First, the Mahanadi, Godavari. Krishna and Kaveri rivers would all be linked by canals. Extra water storage dams would be built along the course of these rivers. The purpose of this would be to transfer surplus water from the Mahanadi and Godavari rivers to the south of India. Second, those rivers that flow west to the north of Mumbai and the south of Tapi would be linked. Due to the irregular fluctuations in water levels in the region, as much storage capacity would be built as possible. The water would be used by the urban areas of Bombay and also to provide irrigation in the coastal areas of Maharashtra. Third the Ken and Chambal rivers would be linked in order to provide better water facilities for Madhya Pradesh and Uttar Pradesh. Finally a number of west-flowing rivers along the Western Ghats simply discharge into the Arabian Sea. As many of these as possible would be diverted for irrigation purposes. The Peninsular part of the project would provide additional irrigation to 130,000 square kilometres and generation an additional 4 gigawatts of power.
Even After 40 Years when Dr.K.L.Rao proposed interlinking Ganges and Kaveri Rivers,still we are dodging and paving the way for the worst dister we faced recently.
Dr.A.Jagadeesh Nellore(AP),India

6 July 2013
Posted by
Dr.A.Jagadeesh

Think again about before advocacy of a dangerously shortsighted policy that will bereft Bangladesh population of more of its legitimate water share, cause an outwards flux of its residents unable to feed themselves, inflame anti-India sentiments to a new level and pave the way to radicalism. Is your water worth all these geo-political headaches ?

8 July 2013
Posted by
Saleh Tanveer

It's amazing that somehow India thinks it can do whatever it needs for its interest, totally disregarding the International laws of Riparian rights of the people downstream.
That the Adivasis within its borders and the 150 plus million people living downstream in Bangladesh needing these waters flowing naturally be damned.

8 July 2013
Posted by
Babul

Post new comment

The content of this field is kept private and will not be shown publicly.
CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.


(Comments are moderated and will be published only after the site moderator’s approval. Please use a genuine email ID and provide your name. Selected comments may also be used in the ‘Letters’ section of the Down To Earth print edition.)
CSE WEBNET
Follow us ON
Follow grebbo on Twitter    Google Plus  DTE Youtube  rss