Madhya Pradesh government lied about rehabilitating people affected by Maheshwar dam

1 Comments
Date:Nov 26, 2012

State now tells green tribunal that developer did not release sufficient funds for resettlement and rehabilitation work

In a surprising turn of events, the Madhya Pradesh government has admitted before the National Green Tribunal (NGT) that the rehabilitation and resettlement (R&R) work of Maheshwar dam oustees is severely neglected. The government, in its submission, blamed private project proponent Shri Maheshwar Hydel Power Company Limited (SMHPCL), a company of the S Kumar’s group, for not releasing R&R funds. The submission made on November 22, which places a letter from the MP Power Management Company on record, states that out of the Rs 740 crore total cost of rehabilitation, only Rs 203.42 crore (27 per cent) has been provided till date.

A press note issued by the Narmada Bachao Andolan (NBA), a people's movement fighting for rehabilitation rights of the oustees, says the government submission makes it clear that earlier submissions, in the form of letters issued by the state secretary for energy Mohammad Suleman, one of which, issued in March 2011, claimed that 70 per cent of R&R work of Maheshwar dam has been completed, were false. The note accused government of first issuing false certification to protect the interests of private promoters and then trying to brush off its own responsibility in this regard by claiming that it is just an agent of the private project proponent.

It may be mentioned here that NBA has earlier pointed out that out of the 60,000 people displaced by the dam, only 15 per cent have been given any kind of rehabilitation package, while not a single person has been given the 2 ha land mandated by the rehabilitation policy, even while 90 per cent of the work of the dam is complete. “The submission regarding just 27 per cent funds being released confirms our contention,” says Alok Agarwal of NBA.

“The worst part is that now it is proved that the state government was all along aware that rehabilitation work was being sidelined, and was hand-in-glove with the private proponent all along,” he added. He said that NBA will challenge the earlier fraudulent certifications before the NGT in future hearings.

NGT orders review of submergence

In its November 22 order, the NGT ordered the committee constituted by  MoEF to look into rehabilitation of Maheshwar dam oustees to visit the dam affected areas to assess damage caused by the filling up of the reservoir up to 155.5 metre on August 7 and 8 this year. On August 9, NGT had permitted SMHPCL to fill the reservoir up to 154 metre, on the condition that there will be no submergence of inhabited land, and had directed state government to complete the rehabilitation process in three months and file and affidavit in this regard. However, government has not carried out the requisite process. Also, hundreds of houses were submerged after the dam was filled up to 154 metre, according to petitioner Antar Singh.

The NBA press note stated that power generated from the Maheshwar dam has turned out to be the most expensive in the country, having been assessed at Rs 9.97 per unit by the Central Electricity Authority. On the other hand, hardly any work has been done to rehabilitate the oustees of the project. Calling the project unviable on all counts, the NBA has demanded that government scrap the project. “It is clear that the proponent has failed to deliver on all counts,” said Agarwal, “And it is only fair that government should scrap its power purchase agreement with the proponent and the public financing agencies who have invested in the project should recover their money.”
 

AddThis

State Government at the level of Secretary, Energy; Chief Secretary, MP and the Chief Minister have in repeated correspondence with the Government of India (at all levels going up to the level of Prime Minister) have testified in 2010 and 2011 that R&R has been achieved till 73% which is why they all put pressure on Government of India that Mr. Jairam Ramesh’s (then Minister for MOEF) stop-order of April, 2010 must be lifted, which it was by May, 2011.

Shree Mahesheshwar Hydel Power Corporation Limited (SMHPCL) has in a PPA agreement and its amendments got MPEB as the executing agency for R&R, for which payment is done by the company on bills raised by MPEB.

In its hearing on Nov 22, 2012, the National Green Tribunal (NGT) also told the council for Government of MP that the State Government cannot get out of its commitment to achieve R&R. Which is why NGT in its order dated August 9, 2012 asked the Government of MP to complete R&R.

27 November 2012
Posted by
Anonymous

Post new comment

The content of this field is kept private and will not be shown publicly.
CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.


(Comments are moderated and will be published only after the site moderator’s approval. Please use a genuine email ID and provide your name. Selected comments may also be used in the ‘Letters’ section of the Down To Earth print edition.)
CSE WEBNET
Follow us ON
Follow grebbo on Twitter    Google Plus  DTE Youtube  rss