Energy

In next 20 years, India may need massive power transmission corridors: CEA

Currently, no new power transmission projects are necessary

 
By Soundaram Ramanathan
Published: Tuesday 26 July 2016
Quadrupling power generation and transmission systems will be needed to meet growing demand. Credit:Oran Viriyincy /Flicker

Central Electricity Authority’s (CEA) report on Advance National Transmission Plan for India, which was released online in mid-July, indicate that the 48 major high-transmission corridors that have already been planned and which are under implementation (expected to be completed by 2017) would be sufficient to meet the import/export of power among various regions till 2021-22.

The report also says that in another 20 years (2035-36), the transmission system needs to be expanded as the demand for power will grow. The all-India peak demand will rise four times from the current level of 153 GW to about 690 GW, hence quadrupling power generation and transmission systems will be required to transmit power, says the report. The report recommends setting up of massive transmission corridors towards northern and southern regions.

However, the CEA is cautious about advising any roadmap, including predicting accurate location for erecting transmission lines and their capacity, because of lack of enough details. The report also pointed out the poor electricity growth, which is in the range of 5-8 per cent per annum.

Regions

Surplus/Deficit (-) Scenario in MW

Inter-state Grid availability in MW

2021-22

2026-27

2031-32

2035-36

as on October 29, 2015

expected by 2017

expected by 2021-22

Northern

-18400

-33200

-54800

-80100

30250

40850

45450

Western

10400

14000

21300

34200

10690

12790

12790

Southern

-7400

-16200

-30100

-47700

11550

15750

30150

Eastern

10900

22300

40600

66600

 

 

 

North-East

1800

2100

3000

4000

2860

2860

2860

All eyes on 19th Electric Power Survey report

For an assertive planning of transmission corridors the authorities are waiting the 19th Electric Power Survey report that will elaborate the power demand and supply situation in India and project requirements for the future. Though the report was expected to be released in April, it is not likely to come out before August.  The estimates of the report will be interesting to look at. The 18th Electric Survey report by CEA has been criticised by reporters for overestimation of power requirement with optimistic GDP figures.

Electricity growth is happening very slowly in India; roughly 40 per cent of installed capacity of coal-fired power stations remains unutilised. As per recent Load Generation Balance report of Central Electricity Authority, power demands have gone down in seven states in 2016 when compared to 2015. In another 16 states, the power requirement has grown by less than 3 per cent.

States

Power Requirement

% Change

2015

2016

Andhra Pradesh

113016

109216

-3.4

D.N. Haveli

5806

5615

-3.3

Himachal Pradesh

9401

9209

-2.0

Sikkim

427

423

-0.9

Uttar Pradesh

111858

110850

-0.9

Karnataka

70294

69781

-0.7

Rajasthan

72132

72070

-0.1

Puducherry

2554

2554

0.0

Jammu & Kashmir

16922

17060

0.8

Chandigarh

1689

1705

0.9

Tamil Nadu

102653

103806

1.1

Punjab

51268

52080

1.6

Arunachal Pradesh

816

830

1.7

Haryana

48870

49800

1.9

Tripura

1425

1453

2.0

Kerala

23703

24179

2.0

Assam

9115

9309

2.1

Delhi

30408

31110

2.3

Jharkhand

9106

9320

2.4

Uttarakhand

13247

13574

2.5

Meghalaya

2155

2215

2.8

Nagaland

825

849

2.9

Maharashtra

149773

154169

2.9

DVC

19224

20365

5.9

Mizoram

502

533

6.2

West Bengal

49654

52867

6.5

Daman & Diu

2221

2372

6.8

Chhattisgarh

24980

27176

8.8

Orissa

26985

29805

10.5

Gujarat

94898

104845

10.5

Madhya Pradesh

65675

74199

13.0

Manipur

865

1008

16.5

Goa

3566

4367

22.5

Bihar

19215

26369

37.2

Mounting losses by state power distribution companies and their inability to procure power are cited as the major reasons for reduced power demand or non-growth of power in the country.

“Central Electricity Authority’s data on power demand only partially captures the actual demand. There exists no count on the number of diesel generator sets operated to compensate the forced power cuts. Of late, no coal power plants are getting planned and average power consumption in India is not growing,” says A KKhurrana, director general, Association of Power Producers. “60 GW of captive power stations operate in India and we are collecting data about these units by encouraging plants to self-disclose,” says N S Mondal, director, Central Electricity Authority.

Reports

Subscribe to Daily Newsletter :
Related Stories

Comments are moderated and will be published only after the site moderator’s approval. Please use a genuine email ID and provide your name. Selected comments may also be used in the ‘Letters’ section of the Down To Earth print edition.