Madhya Pradesh govt cancels all Maheshwar Hydroelectric contracts
Contract awarded projector Rs 42,000 crore of public money in 35 years even if no electricity purchased
Madhya Pradesh threatens to cancel power purchase agreement with Maheshwar dam developer
S Kumars failed to meet operation deadline; all project related activities at a stand-still
Maheshwar dam land acquisition award lapses as developer fails to cough up rehabilitation amount
Officials not clear about the fate of the project
Government considering pumping funds into Maheshwar dam
LIC expresses interest in funding project even as increased capital costs make power from the project too expensive
S Kumars loses defamation appeal against Narmada activists
Narmada Bachao Andolan cites cheating and fraud cases registered by police in support of its press statement against S Kumars and state financial …